Lifting of Furnace No. 4 Dome
Video of the refurbishment of furnace no. 4’s dome, which took place on October 26, 2016.
The dome weighs 38.2 tonnes (84,000 lbs). This project cost $4.3M, and the last refurbishment dated back to 1996.
Video of the refurbishment of furnace no. 4’s dome, which took place on October 26, 2016.
The dome weighs 38.2 tonnes (84,000 lbs). This project cost $4.3M, and the last refurbishment dated back to 1996.