Environmental Regeneration Zone
In March 2023, the Quebec government unveiled an action plan to support Rouyn-Noranda. Measure 1 of this plan provides for the gradual relocation of residents who lived near the Horne Smelter in order to create a buffer space between the smelter and residential neighborhoods.
This area, between 9th Street and 4th Street, from Portelance Avenue to Carter alley, is set to be transformed over the coming years.
What was formerly known as the “buffer zone” is now becoming the Environmental Regeneration Zone.
The ministry requires that this area serve as a separation distance between industrial activities and the surrounding urban area. Rather than leaving a vacant lot, the Horne Smelter wishes to create a living environment: a green, naturalized space designed to promote wildlife, vegetation, and soil regeneration. This vision now guides the project.
Glencore Horne Smelter is responsible for the acquisition, dismantling, and landscaping the site, entirely at its own expense.
-
1. Acquisition
67% as of July 1, 2026 -
2. Dismantling
Work will begin in October 2026 -
3. Landscaping
330 respondents to the first round of consultation
Glencore Horne Smelter is responsible for acquiring properties located within the Environmental Regeneration Zone. As of July 1, 2026, 55 of the 82 properties had been acquired, representing 67%. For details, see the acquisition protocol
Property owners wishing to initiate the sales process may contact the Horne Smelter at the Community Relations Office.
46, 7e Rue, local 104, Rouyn-Noranda (Québec) J9X 1Z7
819 762-7764, extension 2002
Questions about the whole process? Visit the government’s action plan website.
The dismantling of acquired residences is a key step in creating the Environmental Regeneration Zone. It not only helps secure the acquired buildings but also gradually prepares the sites for the next phases of the project.
Only buildings that have been acquired, vacated, and are ready from both a technical and regulatory standpoint will be dismantled. Not all residential buildings will be demolished at the same time. Work will proceed in phases.
The first phase is expected to begin around October 6, 2026 and continue for several weeks.
The work is generally expected to take place from October 6, 2026 to November 30, 2026, from 7:00 a.m. to 7:00 p.m.
Before dismantling, each building undergoes appropriate preparation, which may include:
- Removal of lightweight components (doors, cabinets, light fixtures, etc.) for donation to organizations;
- Inspection and characterization of materials;
- Removal of hazardous materials (e.g., asbestos), when required;
- Cleaning of certain surfaces;
- Safe disconnection of water, electricity, and gas;
- Establishment of a safety perimeter;
- Planning of the demolition method by specialists.
Depending on the needs, the following measures, among others, will be implemented to mitigate potential impacts during the work:
Delimitation of the work zone, notification of traffic obstructions, no work between 7:00 p.m. and 7:00 a.m., coordination with Hydro-Québec, Énergir, and the City to minimize temporary service interruptions, and watering of the work zone.
Glencore Horne Smelter is responsible for landscaping the Environmental Regeneration Zone at its own expense. The land will remain the private property of Glencore (Horne Smelter). Access to the core of the zone will be restricted, as required by the ministry.
Consultation Phase 1: What We Heard
The first phase of consultation on the future of the ERZ is now complete. A total of 330 people participated in the process, including 37 people at the workshops and 293 survey respondents.
The discussions highlighted several key directions to guide thinking on the zone’s future development:
- making greening and naturalization a priority to create a defining green space;
- subtly preserving the site’s history, particularly in how the area’s history and heritage are evoked;
- fostering safe and pleasant connections between the different sectors;
- maintaining a transparent and participatory process so that residents can stay informed and contribute to the next steps.
The comments gathered show, in particular, a marked interest in a large structuring green space, accompanied by a vegetated transition to soften the presence of the smelter, and a sensitive evocation of the site's memory.
The project is now moving forward to transform this collective vision into a concrete, sustainable, and promising development for future generations. No final decision has yet been made regarding the development of the ERZ. The results of this first phase will inform further deliberations and help prepare for Phase 2 of the consultation.
Next opportunity to discuss the project: September 19, 2026 – Recycling Day.
Representatives from the Horne Smelter and consultant Domus Architecture + Design Urbain will be on site to present project updates, answer questions, and continue conversations with the community.
Citizens will also be able to participate through an online survey.
Do you have any questions?
Do you have any questions?
Contact the Horne Smelter Community Relations Office
46, 7e Rue, local 104, Rouyn-Noranda (Québec) J9X 1Z7
infocommunaute@glencore.ca
819 762-7764, poste 2002